FOR YOUR SAFETY
The use and storage of gasoline or other flammable
vapors and liquids in open containers in the vicinity
of this appliance is hazardous.
Modular Packaged Unit
Installation, Operation and Maintenance Manual
Modular Packaged Cooling Unit
Warning!!
Spreader Bar with length matching that of this entire unit Must be used
while hoisting this unit. All lifting lugs must be utilized while hoisting. Manufacturer is
not liable for any damage or injuries resulting from failure to do so.
. This document is the property of the owner of this equipment and is
required for future maintenance. Leave this document with the owner when installation or
service is complete.
RECEIVING AND INSPECTION
Upon receiving unit, check for any interior and exterior damage, and if found, report it
immediately to the carrier. Also check that all accessory items are accounted for and are
damage free. Turn the blower wheel by hand to verify free rotation and check the damper (if
supplied) for free operation.
WARNING!!
Improper installation, adjustment, alteration, service or maintenance can cause property
damage, injury or death. Read the installation, operating and maintenance instructions
thoroughly before installing or servicing this equipment. ALWAYS disconnect power and gas
prior to working on heater.
FOR YOUR SAFETY
If you smell gas:
1. Open windows.
2. Do not touch electrical switches.
3. Extinguish any open flames.
4. Immediately call your gas supplier.
Page view 0
1 2 3 4 5 6 ... 23 24

Summary of Contents

Page 1 - Warning!!

July 2014 Rev. 12 FOR YOUR SAFETY The use and storage of gasoline or other flammable vapors and liquids in open containers in the vicinity of this app

Page 2 - TABLE OF CONTENTS

10 OPERATION Prior to starting up or operating this unit, check all fasteners for tightness. In particular, check the set screw in the wheel

Page 3 - WARRANTY

1113. If the unit is a cooling only unit, adjust the air proving switch such that prevailing winds cannot start the condensers without the blower ope

Page 4 - INSTALLATION

1298°F – 83.5°F = 14.5°F of subcooling This should be compared to the condenser nameplate subcooling, which in this case is 14°F as shown to the righ

Page 5

13If the superheat is too low, and an adjustable-type valve is supplied, the superheat can be increased by turning the adjustment stem in a clockwise

Page 6

14 Sequence of Operation-Cooling with Direct, Indirect, or Electric Heat This unit is most easily understood when broken down into smaller ind

Page 7

15Sequence of Operation-Reheat The unit can be equipped with an optional reheat coil downstream from the DX coil. When this option is installed, war

Page 8 - Copper Wire Ampacity

16• Space Cool SP – Stage 1 space cooling set point. • Space Cool SP #2 – Stage 2 space cooling set point. • Space Cool SP #3 – Stage 3 space cool

Page 9

17• Clear Faults – Once the faults have been resolved, choosing this option will wipe them from the board’s memory. If the fault has not been resol

Page 11

19Components The following image outlines the typical modular packaged unit components. Systems are available with heating modules, mixing boxes an

Page 12 - Superheat and Adjusting TXVs

TABLE OF CONTENTS WARRANTY ...

Page 13

20Troubleshooting The following tables list causes and corrective actions for possible problems with the units. Review these lists prior to consulti

Page 14

21MAINTENANCE To guarantee trouble free operation of this unit, the manufacturer suggests following these guidelines. Most problems associated

Page 15 - Sequence of Operation-Reheat

222. Filters need to be cleaned and/or replaced quarterly, and more often in severe conditions. Washable filters can be washed in warm

Page 16

23Start-Up and Maintenance Documentation START-UP AND MEASUREMENTS SHOULD BE PERFORMED AFTER THE SYSTEM HAS BEEN AIR BALANCED AND WITH THE

Page 17

24Maintenance Record Date Service Performed Factory Serv

Page 18 - Board Menu

3WARRANTY This equipment is warranted to be free from defects in materials and workmanship, under normal use and service, for a period of 12 months f

Page 19 - Components

4INSTALLATION It is imperative that this unit is installed and operated with the designed airflow, gas, and electrical supply in accordance with t

Page 20 - Troubleshooting Chart

5Optional Moisture Eliminator Panel If the unit is equipped with an optional moisture eliminator panel, the maximum face velocity of the coil may be

Page 21 - MAINTENANCE

6 Typical Roof Mount Installation Typical Roof Mount Installation with Exhaust Fan

Page 22

7Plumbing Connections There is one field plumbing connection required for proper DX coil operation. This is the drain pan located u

Page 23 - Unit Information

8Copper Wire Ampacity Wire Size AWG Maximum Amps 14 15 12 20 10 30 8 50 6 65 4 85 1. Always disconnect power before working on or near

Page 24 - Factory Service Department

9MUA/Condenser Fan to Building Wiring Connection Single Phase Condenser: Condenser 1 is the Blue/Blue lines; Condenser 2 is the Red/Red lines; Cond